22 February: this is my view when I first moved in.
Note the circled Hanok.
Here is a closer look.
21 April: A couple months later, I discovered it was being destroyed.
22 April: I went inside and found this calendar turned to December 2012.
23 April: more demolition. It's clear they won't save any of the building materials.
The way in is barricaded.
29 April: They clear out the remaining debris.
30 April: Cleared out.
8 May: the lot has been empty a while, but these little sticks tied with string begin showing up.
11 May: and building materials show up.
12 May: a closer look at the sticks. They're likely tracing the measurements of a future building.
14 May: digging happens
17 May: concrete foundation is poured.
A closer look.
20 May: pipes appear.
21: construction blankets go up.
A closer look.
This appears to be the architect firm.
A very old looking bottle in the dirt.
4 June: Activity resumes on election day.
7 June: more building supplies appear.
13 June: the structure starts to form.
14 June: one wing.
Two wings.
15 June: netting is placed over the structure when they aren't working.
17 June: beams start moving up.
19 June: Those beams are fitting into place.
20 June: Now they are covered by flat pieces of wood.
21 June
22 June: signage out front.
24 June
27 June: another layer on the roof.
28 June: the roof is coated in clay and tiling begins.
30 June
1 July
Click for an animated GIF
|